How to Do a Concrete Takeoff From PDF Drawings

Do a concrete takeoff from PDF drawings: measure footings, slabs and walls, convert to cubic yards, add a sourced overage, then rebar by weight and forms.
Published
A concrete takeoff measures every footing, slab, wall, pad and step on the drawings, multiplies each one out to cubic feet, divides by 27 to get cubic yards, and adds an overage before you order. Rebar is taken off by weight and formwork by contact area from the same measurements.
Below are the formula for each element and one small foundation carried to cubic yards, pounds of rebar and square feet of forms.
What is the formula for a concrete takeoff?
The formula for concrete volume is length x width x depth, with all three in feet, which gives cubic feet. Divide by 27 to get cubic yards, because one cubic yard is 3 ft x 3 ft x 3 ft. Ready-mix is sold in cubic yards in the US (cubic meters in Canada), so every element ends up in that unit.
What you measure on the page changes by element:
| Element | What you measure on the PDF | Formula (feet) |
|---|---|---|
| Continuous (strip) footing | Centerline length | Length x width x depth |
| Pad (spread) footing | Count of each pad type | Count x length x width x depth |
| Slab on grade | Area, net of openings | Area x thickness |
| Thickened slab edge | Perimeter length | Length x extra depth x width of thickening |
| Wall or stem wall | Centerline length | Length x height x thickness |
| Square or rectangular column | Count | Count x width x depth x height |
| Round column or pier | Count and diameter | Count x 3.1416 x radius x radius x height |
| Steps | Count of risers, or the side profile area | Profile area x stair width |
Convert inches to decimal feet before you multiply: 4 in. is 0.333 ft, 6 in. is 0.5 ft, 8 in. is 0.667 ft.
What do you check before you measure?
Read the structural general notes, the foundation plan, the sections and the specification before you take off anything. The plan shows the footprint of each element, while depth, width and thickness are usually only in the sections, the footing schedule or the notes.
- Find the footing schedule and sections, and note the width and depth of every footing and the thickness of every wall.
- Read the slab notes for thickness, thickened edges, depressed areas and the vapor barrier and base.
- Note which elements use which mix, since different strengths are priced and ordered separately.
- Set the scale on every PDF page you will measure and check it against a printed dimension. How to Scale a PDF Drawing for Accurate Takeoffs covers both methods and how to verify.
- Where a dimension is written on the drawing, use the written number over a scaled measurement. Measure to get lengths the drawing doesn't dimension, and to check totals.
Keep one line on your takeoff sheet per element type and mix, so the cubic yards match how the concrete is ordered.
How do you measure each concrete element?
Measure linear elements (footings, walls, thickened edges) as lengths, flat elements (slabs) as areas, and repeated elements (pads, columns, piers) as counts. Then apply the cross-section from the schedule or section to each.
Continuous footings and walls
Trace the centerline of the footing or wall around the building, so each corner is counted once. Take each footing or wall type as its own measurement, since a 24 in. footing and a 30 in. footing can't share a line.
For a stepped footing, measure each level as its own run and add the vertical step as a small block (step height x footing width x footing depth).
Slabs
Measure each slab area and deduct openings such as pits and blockouts. A different thickness, depressed area or mix gets its own area. A thickened or turned-down edge is extra concrete below the slab: take it as a linear run around the perimeter, with the extra depth and width from the section.
Pads, columns and piers
Count each pad footing type from the footing schedule marks on the plan, then multiply the count by one pad's volume. Do the same for columns and piers, using the height from the sections or the floor-to-floor height.
Steps, ramps and sloped slabs
For steps, multiply the area of the side profile by the stair width. For a steep ramp or sloped slab, use the slope length from the section rather than the plan length.
Common misses
Check for: thickened edges and depressed slabs, the vertical concrete at stepped footings, openings deducted from slabs, embeds and anchor bolts counted by type, lap splices and dowels, and each mix kept separate with its own overage. When a revised set arrives, compare the two PDF drawings before you reuse the takeoff.
How do you convert to cubic yards and add overage?
Add the cubic feet for each element, divide by 27, then add an overage for waste and placement over the plan dimensions. Two published figures to set against your own job history:
- The National Ready Mixed Concrete Association says to order 4% to 10% more than an estimate calculated from the plan dimensions (NRMCA CIP 31, Ordering Ready Mixed Concrete, revised 2023). Its sheet on yield adds that sporadic work alternating between slabs, footings, walls and fill around pipes needs a bigger allowance than repetitive work (NRMCA CIP 8, Discrepancies in Yield, 2016).
- Cemex's ready-mix calculator says to add 10% to 15% to the order for spillage, uneven subgrade and other variables (Cemex US concrete calculator, checked November 2026).
CIP 8 also shows why small errors matter: an extra 1/8 in. on a 4 in. slab is a 3% shortage, or about 1 cu yd on a 32 cu yd order. The other causes it lists are forms that bow under the concrete and placement on irregular subgrade or fill.
CIP 31 puts truck mixer capacity at 8 to 12 cu yd (5 to 9 m³), and advises re-checking the quantity near the end of a pour so the last loads can be adjusted.
How do you take off rebar and wire mesh?
Rebar is taken off by weight: count the bars of each size, multiply by the length of each bar, then multiply the total length by the bar's weight per foot. Weights per foot are standard for each bar size.
| Bar size | Diameter (in.) | Weight (lb/ft) |
|---|---|---|
| #3 | 0.375 | 0.376 |
| #4 | 0.500 | 0.668 |
| #5 | 0.625 | 1.043 |
| #6 | 0.750 | 1.502 |
| #7 | 0.875 | 2.044 |
| #8 | 1.000 | 2.670 |
Source: Ohio Department of Transportation, Construction and Material Specifications Item 509, Table 509.05-1 (2013 edition).
- For continuous bars, multiply the number of bars shown in the section by the run length you already measured for the footing or wall.
- For bars at a spacing, divide the run length by the spacing to get the number of bars, then multiply by the length of each bar, including hooks and bends shown in the details.
- For slab mats, count the bars in each direction from the spacing and the slab dimensions, and add a bar at the end of each run.
- Add lap splices for continuous bars longer than stock lengths. The lap length depends on bar size, concrete strength and location, and it comes from the structural drawings or general notes. Don't use a rule-of-thumb number.
- Add dowels, corner bars and the bars around openings shown in the details.
Welded wire reinforcement is taken off by area from the slab measurement, plus the overlap at the edges of each sheet or roll that your specification requires. Use the overlap stated in the specification or the manufacturer's data. Count embeds, anchor bolts and hold-downs by type.
How do you take off formwork?
Formwork is measured as contact area: the square feet of concrete face that a form touches. Multiply each formed edge's length by its height, and count both faces of a wall. Footings poured against the excavation (earth-formed) need no side forms, so check the section or ask the contractor before you include them.
| Element | Contact area |
|---|---|
| Strip footing (formed) | Length x depth x 2 sides |
| Pad footing (formed) | Perimeter of the pad x depth, per pad |
| Wall | Length x height x 2 faces |
| Slab edge | Perimeter x slab thickness (plus the thickened edge depth) |
| Column | Perimeter of the column x height |
Worked example: a small foundation and slab
Every dimension here is a placeholder chosen to keep the arithmetic readable, not a typical value.
The building has a perimeter strip footing 2 ft wide and 1 ft deep under an 8 in. stem wall 3 ft high, both 140 ft long at the centerline. Inside the walls is a slab 4 in. thick, and four interior pad footings are 3 ft x 3 ft x 1 ft. To keep the numbers round, the slab is taken at the 30 ft x 40 ft centerline size. On a real job, measure it to the inside face of the walls (29.33 ft x 39.33 ft here, about 385 cu ft instead of 400).
Concrete
| Element | Calculation | Cubic feet |
|---|---|---|
| Strip footing | 140 x 2 x 1 | 280 |
| Pad footings | 4 x 3 x 3 x 1 | 36 |
| Stem wall | 140 x 0.667 x 3 | 280 |
| Slab | 30 x 40 x 0.333 | 400 |
| Total | 280 + 36 + 280 + 400 | 996 |
| Cubic yards | 996 / 27 | 36.9 cu yd |
| With 4% overage | 36.9 x 1.04 | 38.4 cu yd |
| With 10% overage | 36.9 x 1.10 | 40.6 cu yd |
Round the order up to full loads. If the footings and walls use one mix and the slab another, split the total by mix first and add overage to each.
Rebar
The placeholder reinforcing is three continuous #4 bars in the footing, #4 vertical dowels at 16 in. on center in the wall, each 4 ft long, and #3 bars at 18 in. on center each way in the slab.
| Item | Calculation | Pounds |
|---|---|---|
| Footing bars | 3 x 140 ft = 420 ft x 0.668 | 280.6 |
| Wall verticals | 140 x 12 / 16 = 105 bars x 4 ft = 420 ft x 0.668 | 280.6 |
| Slab bars, long way | 30 x 12 / 18 + 1 = 21 bars x 40 ft = 840 ft x 0.376 | 315.8 |
| Slab bars, short way | 40 x 12 / 18 + 1 = 28 bars (rounded up) x 30 ft = 840 ft x 0.376 | 315.8 |
| Total before laps | 1,192.8 lb |
Laps on the 140 ft footing bars and 40 ft slab bars come next, at the lap length on the drawings.
Formwork
| Item | Calculation | Square feet |
|---|---|---|
| Strip footing sides | 140 x 1 x 2 | 280 |
| Pad footing sides | 4 x 12 ft perimeter x 1 | 48 |
| Stem wall faces | 140 x 3 x 2 | 840 |
| Total contact area | 1,168 sq ft |
The slab is poured inside the stem walls, so it has no edge form here.
How do you do a concrete takeoff on a PDF in Notch?
In Notch, the PDF editor we make, you measure each element on the page with the Linear, Area, Volume and Count tools, give each one a name and cost code, and export the list as a CSV. Notch measures lengths, areas, volumes and counts. The overage, rebar weights and form reuse are arithmetic you do on the exported quantities.
- Open the PDF, click Set scale in the status strip and pick the scale or calibrate from a dimension. Check it against a second printed dimension.
- For a slab, choose Volume from the Measurements flyout (
⇧⌥V), set the Depth in Properties (for example 4 in.) and click the corners of the slab. The value reads in cubic feet. Change the measurement's display unit in Properties to yd to read it in cubic yards. - For a slab with openings, measure it with Area and take the openings out with Cutout, then multiply the net area by the thickness after export.
- For footings and walls, trace the centerline with Linear (
M). Enter a Height in Properties (the footing depth, or the wall height) and Notch shows the Wall area of one face, which is the form contact area for that side. Multiply by the width or thickness for concrete, and by 2 for both faces. - For pad footings, columns and embeds, use Count, one count group per type. A count group spans every page of the document.
- Give each measurement a name, cost code and division in Properties. Then open the Measurements panel, use Group & sort to group by cost code or layer, and click Export CSV. The CSV has the value, unit and wall area for each measurement.

The measurements and calibration docs cover every tool, and the worksheet docs cover custom columns and export. For tracing slab areas with deductions, see How to Measure Area on a PDF. Measurements are part of the Solo and Pro plans, with a 14-day trial (see pricing). They depend on the scale, and the contract documents govern.
Frequently asked questions
How do you calculate cubic yards of concrete?
Multiply length x width x depth with all three in feet to get cubic feet, then divide by 27. A 30 ft x 40 ft slab 4 in. thick is 30 x 40 x 0.333 = 400 cu ft, and 400 / 27 = 14.8 cu yd before overage. Convert inches to decimal feet before multiplying.
How much extra concrete should you order?
NRMCA's CIP 31 says to order 4% to 10% more than an estimate calculated from the plan dimensions, and its CIP 8 says sporadic work needs more than repetitive work. Cemex's calculator suggests 10% to 15%. Your own record of ordered against placed quantities on past jobs is the best guide.
What should a concrete takeoff include?
A complete concrete takeoff includes the volume of every footing, pad, wall, column, slab and step, split by mix; rebar by weight with laps; wire mesh by area; formwork by contact area; and counts of embeds and anchor bolts.
Can you do a concrete takeoff from a PDF?
Yes. Set the scale on each PDF page, measure footings and walls as lengths, slabs as areas or volumes, and pads as counts, then apply the depths and thicknesses from the sections. A PDF takeoff tool such as Notch does the measuring, and the CSV goes into your spreadsheet for overage, rebar and forms.
Next steps
Start with the foundation plan and one section: scale the page, measure the footing runs and the slab, and carry them to cubic yards with the table above. The general method for any trade is in How to Do a Takeoff From a PDF, Step by Step, and Drywall Takeoff From a PDF applies the same approach to walls and ceilings. Takeoff in Notch covers the measure tools, count groups and the Measurements panel.