How to Do an Electrical Takeoff From PDF Drawings

Do an electrical takeoff from PDF drawings: count devices and fixtures by type, measure conduit with drops and home runs, then work out wire by conductor.

Published

An electrical takeoff is the list of every device, fixture, piece of gear, box, conduit run and length of wire on the electrical drawings, counted and measured so it can be priced. From a PDF set you read the legend and schedules, set the scale on each page, count devices and fixtures by type, measure conduit runs and add the vertical drops, then work out wire from the conduit lengths.

How do you do an electrical takeoff, in short?

An electrical takeoff from PDF drawings takes five steps, in this order. Labor units and pricing come afterward, in the estimate.

  1. Read the E-series sheets, the symbol legend, the fixture and panel schedules and Division 26 of the specification.
  2. Set the scale on every PDF page you will measure, and check it against a printed dimension.
  3. Count each device and fixture type as its own group, and check the fixture counts against the fixture schedule.
  4. Measure conduit runs on the plan, then add the vertical drops to devices and the runs back to the panel.
  5. Multiply each run by the number of conductors in it to get wire, add makeup at the boxes, then add your allowance.

What does an electrical takeoff include?

An electrical takeoff includes everything you price by the each (devices, fixtures, gear, boxes, fittings) and everything you price by the foot (conduit, cable, wire, cable tray). Each item is a separate line, split by type, size and anything else that changes the price.

CategoryExamplesMeasured asWhere to find it
Wiring devicesDuplex and GFCI receptacles, switches, dimmers, occupancy sensorsCount by typePower and lighting plans, legend
Light fixturesTroffers, downlights, exit signs, emergency fixturesCount by fixture typeLighting plans, fixture schedule
GearPanelboards, transformers, disconnectsCount by size and ratingPower plans, single-line diagram, panel schedules
Boxes and fittingsDevice boxes, junction boxes, connectors, couplings, strapsCount, or derived from devices and runsPlans, details, your firm's standards
ConduitEMT, PVC, rigid, flex, by trade sizeLinear feetPlans, risers, details
Wire and cableBuilding wire by size and color, MC cableLinear feetPanel schedules, plans, home run arrows
Low voltageData outlets, cable tray, sleevesCount and linear feetTelecom and low-voltage plans, if in your scope

Read the scope letter or bid form first: low voltage, fire alarm and temporary power are not always in the electrical contract.

Which sheets do you need before you count?

You need every sheet in the electrical series and the parts of other trades that drive electrical work. The plans show where things are; the schedules, single-line diagram and specification say what each thing is.

  1. Legend and general notes. Note how the set draws conduit in the ceiling, in the floor and exposed, and which symbols look alike.
  2. Power plans. Receptacles, equipment connections, home run arrows and circuit numbers.
  3. Lighting plans and reflected ceiling plans. Fixture types, switching and ceiling heights. Ceiling heights set the length of your drops.
  4. Fixture schedule. Type, description and mounting for each fixture. Some schedules list quantities, which you will use as a cross-check.
  5. Panel schedules and the single-line diagram. Each circuit's breaker, the wire and conduit size for feeders, and which panel each home run goes to.
  6. Details and risers. Mounting heights, typical box and conduit details, and vertical runs between floors.
  7. Specification, Division 26. Which raceway types are allowed where, the minimum wire size and whether MC cable is acceptable.
  8. Mechanical and plumbing plans. Equipment that needs a power connection, such as rooftop units, water heaters and exhaust fans.

Then set the scale on each PDF page and check it against a printed dimension before you measure anything. How to Scale a PDF Drawing for Accurate Takeoffs covers both methods and how to verify.

How do you count devices and fixtures on a PDF?

Count each item type as its own group, one type at a time across every page, and keep look-alike symbols in separate groups. A count needs no scale, only a clear list of types.

  1. Write the list of types from the legend and the fixture schedule. Fixture types A, B and EM are three groups, not one.
  2. Count the less common look-alike first, such as GFCI receptacles before duplex receptacles, so each GFCI is not caught in the duplex count.
  3. Count each area of the building on one plan only. Enlarged plans and match lines are where double counts happen.
  4. Count gear from the single-line diagram as well as the plans, so a panel or disconnect shown on one but not the other gets caught.
  5. Check fixture totals against the fixture schedule where it lists quantities. If they disagree, recount, then send a question to the design team. The contract documents govern which one you price.

How to Count Items on a PDF Drawing covers count groups, fixing a miscount and per-page totals in detail.

How do you measure conduit and wire runs?

Measure conduit in three parts: the horizontal runs between boxes on the plan, the vertical drops from the ceiling to each device, and the home runs back to the panel. Then get wire by multiplying each run's length by the number of conductors in it.

Horizontal runs

Many electrical plans don't draw branch circuit conduit at all, or draw it only as a schematic arc between devices. Measure the path the conduit will take, along walls and at right angles, not the straight line between symbols. Keep each raceway type and trade size as its own measurement, because 1/2 in. EMT and 3/4 in. EMT are priced separately.

Vertical drops

The plan doesn't show vertical conduit, so add it as a count times a length. A drop from conduit in the ceiling space to a receptacle is the height of the conduit above the floor minus the device's mounting height. Take both from the reflected ceiling plan, the mounting height details or the specification, and write them on your takeoff sheet as a project assumption. Where a circuit drops into a box and continues to the next device, count the drop twice (down and back up) or measure the run along the wall instead, and say which. Devices fed from below, such as floor boxes, have their own length.

Home runs

A home run arrow on the plan shows that a circuit goes back to a panel, but rarely shows the route. Measure from the last box on the circuit to the panel along the likely path, and add the rise or drop at the panel. Check the arrow's circuit numbers against the panel schedule so every circuit on the schedule has a home run.

Wire from conduit length

Wire length for a run = conduit length x number of conductors in the run, plus makeup at each box.

A branch circuit with a hot, a neutral and a ground is three conductors. A home run carrying two circuits, each with its own neutral, plus one ground is five. Get the conductor count from the panel schedule, the circuit numbers on the home run arrows and your firm's wiring standards. Makeup is the extra length left in each box for terminations: use your firm's standard per box and state it.

How many conductors fit in a trade size is set by the National Electrical Code, NFPA 70: Chapter 9, Table 1 gives the maximum fill by number of conductors, and Annex C lists conductor counts per trade size. Use the edition your jurisdiction has adopted, and the conduit sizes on the drawings.

Worked example: a small office fit-out

Every number here is a placeholder chosen to keep the arithmetic readable, not a typical value for a real job.

The fit-out is one floor with one panel. The conduit runs in the ceiling space 10 ft above the floor, receptacles mount at 1 ft 6 in. and switches at 4 ft, each fed by one drop. Branch circuits are 1/2 in. EMT with three #12 conductors (black, white, green). Home runs carry two circuits each, five conductors.

Counts

ItemGroupCount
Duplex receptacleDevices32
GFCI receptacleDevices4
Single-pole switchDevices10
Fixture type A, 2x4 trofferFixtures24
Fixture type B, downlightFixtures12
Fixture type EM, emergencyFixtures3
PanelboardGear1
Device boxesBoxes46

Device boxes are one per receptacle and switch: 32 + 4 + 10 = 46. Fixture connections follow your firm's standard and are left out here.

Conduit

RunCalculationFeet
Receptacle horizontal runsMeasured on the plan420
Receptacle drops36 x (10 - 1.5) = 36 x 8.5306
Lighting horizontal runsMeasured on the plan380
Switch drops10 x (10 - 4) = 10 x 660
Home runsMeasured: 55 + 70 + 85210
Rise at the panel3 x 39
Total before allowance1,385

Wire

RunCalculationFeet of wire
Receptacle circuits(420 + 306) x 3 conductors2,178
Lighting and switch circuits(380 + 60) x 3 conductors1,320
Home runs(210 + 9) x 5 conductors1,095
Makeup at device boxes46 boxes x 3 conductors x 2 ft276
Total before allowance4,869

The example keeps each switch drop at three conductors to keep the arithmetic simple. On a real job, count the conductors each switch leg actually carries from the drawings and specification.

Wire is ordered by size and color, so split the total. The branch circuits carry one black, one white and one green conductor. The home runs carry two black, two white and one green.

ColorCalculationFeet
Black726 + 440 + (219 x 2) + 921,696
White726 + 440 + (219 x 2) + 921,696
Green726 + 440 + 219 + 921,477
Total4,869

Allowance

The allowance for waste, offcuts and routing is your firm's choice, based on your own record of ordered against installed quantities. It is not a code or industry standard. Put it on its own line so a reviewer can see it. At a placeholder 5%, conduit is 1,385 x 1.05 = 1,454.25, rounded up to 1,455 ft, and wire is 4,869 x 1.05 = 5,112.45, rounded up to 5,113 ft. Steel EMT comes in 10 ft and 20 ft lengths (Wheatland Tube steel EMT submittal sheet, checked November 2026), so in 10 ft lengths 1,455 ft is 146.

Fittings follow from the same numbers: couplings from the number of lengths, connectors at each end of each run into a box, and straps at your firm's spacing.

How do you check an electrical takeoff?

Check an electrical takeoff against the fixture and panel schedules, confirm every page was counted, and compare against the latest revision. Common errors are a missed sheet, a double count at a match line, or a circuit with no home run.

  1. Compare each fixture type's count with the fixture schedule.
  2. Compare the circuits on the panel schedule with your home runs, so no circuit is missing.
  3. Confirm every sheet in the set has been counted and measured, including enlarged plans and site plans.
  4. Check equipment connections against the mechanical and plumbing equipment schedules.
  5. Recheck the scale on any page whose lengths look off.
  6. When a revised set arrives, compare the two PDF drawings and update only what changed.
  7. Read your assumptions list once more: ceiling height, mounting heights, conductors per home run, makeup and allowance.

How do you do an electrical takeoff on a PDF in Notch?

In Notch, the PDF editor we make, you count devices and fixtures with Count, measure conduit runs with Linear, give each measurement a name and cost code, and export the list as a CSV. Notch counts and measures. Drops, wire by conductor, the allowance, labor and pricing are arithmetic you do on the exported quantities.

  1. Open the PDF and click Set scale in the status strip. Pick the scale or calibrate from a dimension, then check it against a second printed dimension. Do this on each page, because calibration is per page.
  2. Choose Count from the Measurements flyout (⇧⌥C). Name the group in Properties, such as "GFCI receptacle", pick a symbol and color, and click each one. A count group spans every page of the document.
  3. Choose Count again for the next type. Each new count starts a new group.
  4. Choose Linear (M) and click along each conduit route. Keep clicking to trace a running length. Start a separate measurement for each raceway type and trade size.
  5. Give each measurement a cost code and division in Properties, and put the electrical takeoff on its own layer.
  6. Open the Measurements panel, use Group & sort to group by cost code or page, and click Export CSV. The CSV has one row per measurement, with its value, unit and page.

The Worksheet (Ctrl+Shift+L, ⌘⇧L on Mac) shows the same list as a table with filters, grouping and custom columns, and exports it as set up. The Electrical library in the Tool chest has device symbols and circuit line types such as Conduit (ceiling) and Homerun to panel for marking up a set. Those are markups, so take quantities with the measure tools.

The Measurements panel listing named measurements with totals, a garage slab area and a patio edge form perimeter

The measurements and calibration docs cover every tool, and the worksheet docs cover custom columns and export. Measurements are part of the Solo and Pro plans, with a 14-day trial (see pricing). They depend on the page scale, and the contract documents govern.

Frequently asked questions

What is an electrical takeoff?

An electrical takeoff is a list of the quantities of every electrical item on a project's drawings: devices, light fixtures, panels and other gear counted by type, and conduit, cable and wire measured in linear feet. Estimators take it from the drawings and specification, then apply labor units and prices in the estimate.

How do you calculate wire from conduit length?

Multiply each conduit run's length by the number of conductors in it, then add makeup at each box. A 100 ft branch run with a hot, a neutral and a ground is 300 ft of wire before makeup. Split the total by wire size and color, since each is ordered separately.

How much waste should you add to an electrical takeoff?

There is no code or industry standard waste factor for conduit or wire. The allowance is your firm's choice, based on what you ordered against what was installed on past jobs. Put it on its own line in the takeoff so anyone checking it can see the assumption.

Can you do an electrical takeoff from a PDF?

Yes. Set the scale on each PDF page, count devices and fixtures with a count tool, and measure conduit runs with a length tool. A PDF editor with measurement tools, such as Notch, does the counting and measuring, and the CSV goes to your spreadsheet or estimating software.

Next steps

Start with one floor: read the legend and panel schedule, count the devices and fixtures, measure the conduit, and carry it to wire with the tables above. The general method for any trade is in How to Do a Takeoff From a PDF, Step by Step, and Drywall Takeoff From a PDF applies it to walls and ceilings. Takeoff in Notch covers count groups, the measure tools and the Measurements panel.

Leave the desktop behind. Keep the capability.

Free plan · or try Solo or Pro free for 14 days