What Is an RFI in Construction? How to Write One

An RFI in construction is a written question about the drawings or specs. How the process works, how to write a good one, and RFI vs submittal vs ASI.
Published
An RFI in construction (request for information) is a written question the contractor sends to the design team when the drawings or specifications are unclear, conflict with each other or don't match the site. The general contractor usually sends it, often for a subcontractor. The architect or engineer of record answers it. An RFI asks for clarification. It does not change the contract price or schedule by itself.
What is an RFI in construction?
An RFI is a formal, numbered, logged question about the contract documents. It asks the person responsible for the design to interpret something, fill a gap or resolve a conflict, and it asks for the answer in writing so everyone builds from the same information.
Some firms read RFI as "request for interpretation", which is closer to what most RFIs do. CSI's MasterFormat 2020 lists both meanings for the abbreviation, and puts the specification section for the RFI procedure at 01 26 13 Requests for Information in Division 01, according to a CSI article on interpretations and clarifications (July 2025, checked November 23, 2026).
An RFI is not:
- A request for approval. Shop drawings and product data go through submittals.
- A change order. An RFI answer can lead to one, but the RFI itself doesn't change the price or time.
- A procurement document. An RFP or RFQ goes out before award to get prices. An RFI in construction happens during the job.
Why do RFIs come up?
RFIs come up whenever the contractor can't build from the documents as drawn without guessing:
- A dimension, elevation or detail is missing.
- Two drawings disagree, often across disciplines: the mechanical plan puts a duct where the structural plan puts a beam.
- The drawings and the specifications disagree.
- Field conditions don't match the drawings, common in renovation work.
- A specified product is discontinued or won't fit.
- The contractor spots something that appears not to meet code.
Who does what on an RFI?
Roles depend on the contract. On a typical design-bid-build job under AIA documents:
| Who | What they do on an RFI |
|---|---|
| Subcontractor | Finds the issue in the field or in coordination, drafts the question, proposes a fix |
| General contractor (PM or project engineer) | Reviews and edits the sub's draft, numbers and logs it, sends it to the architect, tracks the due date, distributes the answer |
| Architect | Receives the RFI, answers or routes it to the right consultant, issues the written response |
| Engineer or consultant | Answers questions in their discipline (structural, MEP, civil) through the architect |
| Owner | Decides on anything that changes cost or time; signs change orders |
Subs rarely send RFIs straight to the architect. The question goes up the contract chain and the answer comes back down it.
How does the RFI process work?
The RFI process runs from finding the problem to closing the log entry. Most projects follow these steps, with the format and timing set by the contract and the Division 01 specifications.
- Spot the issue. In coordination, during layout, or when something on site doesn't match.
- Check the documents first. Read the related sheets, details, schedules and spec sections. Many RFIs are answered somewhere in the set already.
- Draft one question. State the problem, where it is and what you propose.
- Attach the marked-up page. Cloud the area, label it with the RFI number, and include photos if the issue is a field condition.
- Number and log it. The GC gives it the next number and records the date sent and the date the answer is needed.
- Send it through the contract chain. Sub to GC, GC to architect, architect to consultant.
- Get the answer in writing. Sometimes with a sketch or a revised sheet.
- Distribute the answer to every trade it affects, and update the field set.
- Close it in the log, or keep it open if the answer raised a follow-up.
- Flag cost or time. If the answer changes the work, it moves into the change process.
How do you write a good RFI?
A good RFI asks one clear question, points to the exact place in the documents, explains why the documents don't work as drawn, proposes a solution and says when you need the answer. Use this checklist before you send one:
- One question per RFI. Split anything that needs two answers.
- A subject line that names the location and the problem: "Level 2, grid C/4: supply duct conflicts with beam".
- References: sheet number and revision, detail number, grid lines, room number and spec section.
- What the documents say, in their words, and why it doesn't work.
- Your proposed solution, so the designer can answer "approved" or correct it.
- The date you need the answer and the reason (the activity it holds up).
- The marked-up page and any photos, with the RFI number on the markup.
- Whether you believe the answer could affect cost or time.
- Who drafted it and who on the GC's team reviewed it.
Example: a vague RFI rewritten
The example below is invented for illustration.
Before
RFI 047: Duct and beam conflict on 2nd floor. Please advise.
After
RFI 047: Level 2, grid C/4. Supply duct SD-3 conflicts with beam W16x26
References: M-201 rev 2 (duct shown at 14'-0" BOD); S-201 rev 3 (beam
bottom of steel at 13'-8"); spec 23 31 13
Problem: The 24"x14" duct run on M-201 passes through the beam on S-201.
There is no room to drop the duct; ceiling is at 12'-6" per A-301.
Proposed: Transition SD-3 to two 24"x7" ducts under the beam for 6'-0",
per the attached markup. Confirm the airflow is acceptable.
Needed by: December 4 (ductwork rough-in on Level 2 starts December 8)
Cost or time impact: Possible (added fittings), to be confirmed
Attached: M-201 rev 2 marked up, clouded at C/4; site photoIf the engineer agrees, the rewritten version can be answered in one word. The first version needs a phone call and probably a second RFI.
Common RFI mistakes
- Several questions in one RFI. The answer comes back for the easy one and the hard one stays open.
- "Please advise" with no proposal. It puts the whole problem back on the designer and slows the answer.
- An RFI used to fish for a change order. A cost question belongs in the change process, not in an RFI.
- An answer given by phone and never logged. There is no record of it when the work is questioned later.
- Marking up a superseded sheet. Check the revision first. When the answer comes back as a revised sheet, compare two PDF drawings to see what changed.
How do you mark up the drawing for an RFI?
The drawing that goes with an RFI shows the reviewer exactly where the problem is, so the question can't be read two ways.
- Use the current revision. Check the title block and revision schedule before you mark anything.
- Cloud the area in question. Keep the cloud tight to the conflict. See how to add revision clouds to a PDF.
- Add a callout with the RFI number and a one-line question. "RFI 047: duct SD-3 hits beam at C/4".
- Show the grid lines and the related view. If two disciplines conflict, mark both sheets, or overlay them.
- Draw the proposed fix in a different color, with a short note.
- Export only the pages the RFI needs, with the title block showing so the sheet number and revision travel with it.
For markup conventions (colors, layers per reviewer, what to send back), see how to redline a PDF drawing.
Mark up the RFI page in Notch
Notch, our PDF editor, is where the drawing half of an RFI gets done. It does not manage RFIs: Notch has no RFI log, numbering, routing, due dates or ball-in-court tracking. Teams track RFIs in a project management tool such as Procore or Autodesk Build, or in a spreadsheet log, and use Notch to mark up the page that goes with each one. The Notch and Procore comparison explains how the two split the work.
- Open the PDF in Notch and go to the page in question.
- Draw the cloud: Shapes > Revision cloud (C).
- Add the question: Text > Callout (Q), point the leader at the conflict and type the RFI number and question. Sequence (Shift+N) drops running numbers if you tag several RFIs on one page.
- Put the round's marks on their own layer: Layers > New layer, for example "RFIs".
- To ask a teammate first, open Discussion, pin a comment to the spot and @mention them.
- Export the page: Export… from the n menu, Pages > Current page, then Flattened for the record or Unflattened if the architect will mark it up in Bluebeam or Acrobat.
- Or send a view link: Share > Link sharing > New link > View link. It opens without a Notch account.
According to the Notch markups docs, the Free plan includes shapes (the revision cloud included), callouts, text boxes and comment pins; Sequence and creating layers need Solo or Pro. Discussion, view links and exports work on every plan. See Notch pricing.
The worksheet (Ctrl+Shift+L) lists every RFI markup on the document, filtered by layer or status. It is a list of markups, not an RFI log.
RFI vs submittal vs ASI vs change order
An RFI asks a question. A submittal shows how the contractor plans to meet the design. An ASI is the architect's instruction or interpretation with no change to price or time. A change order changes the contract, and a construction change directive orders a change before price and time are agreed.
| Document | Purpose | Who issues it | Changes cost or time? | AIA form |
|---|---|---|---|---|
| RFI (request for information) | Asks for clarification of the documents | Contractor (or owner, architect, other party) | No, by itself | G716–2004 |
| Submittal | Shows how the contractor will meet the design (shop drawings, product data, samples) | Contractor, for the architect's review | No | None (no G-series form) |
| ASI (architect's supplemental instructions) | Additional instructions or interpretations, or minor changes | Architect | No | G710–2017 |
| Change order | Agreed change to the work, price and time | Prepared by the architect, signed by owner, contractor and architect | Yes | G701–2017 |
| CCD (construction change directive) | Orders a change before price or time is agreed | Prepared by the architect, signed by owner and architect | Yes, adjusted later | G714–2017 |
AIA forms checked November 23, 2026. AIA's G716 summary says "Neither the request nor the response received provides authorization for work that increases the cost or time" of the project, and its G710 instructions say G710 "should not be used to change the contract sum or contract time."
A201–2017 §3.12.4 says submittals "are not Contract Documents". An RFI answer often comes back as an ASI or a sketch; if it changes the work, it becomes a change order or a CCD.
What does the contract say about RFIs?
In the AIA A201–2017 general conditions, RFIs are the way the contractor reports errors, omissions and code issues it finds in the documents, and the architect answers them in writing. The response time is whatever the contract sets, or "reasonable promptness" if it sets none. The clauses below are quoted from A201–2017 (checked November 23, 2026; AIA's A201 summary).
- §3.2.2: the contractor reports "any errors, inconsistencies or omissions discovered by or made known to the Contractor as a request for information in such form as the Architect may require." The same clause says the contractor's study of the documents is for coordination, "not for the purpose of discovering errors, omissions, or inconsistencies."
- §3.2.3: the same applies to any code nonconformity the contractor finds, though the contractor "is not required to ascertain" that the documents meet code.
- §3.2.4: if the contractor believes the architect's clarifications or instructions in response add cost or time, it submits Claims under Article 15.
- §4.2.14: the architect "will review and respond to requests for information about the Contract Documents," in writing, "within any time limits agreed upon or otherwise with reasonable promptness," and may issue supplemental drawings and specifications in response.
In practice, the specific response time (a number of working days, and how far ahead of the need date an RFI should be sent) is set in the owner-contractor agreement or in the Division 01 RFI section of the project specifications. There is no industry default. ConsensusDocs, EJCDC and owner-written contracts set their own terms. In Canada, CCDC contracts use their own terms, and the Ontario Association of Architects publishes a model RFI specification section for CCDC 2 contracts (checked November 23, 2026).
This is how the standard form reads, not advice on any contract. Check your own agreement with your contracts lead or lawyer.
What goes in an RFI log?
An RFI log is the running list of every RFI on the job, usually kept by the GC's project engineer, in a project management tool or a spreadsheet. Most logs carry these fields:
| Field | What goes in it |
|---|---|
| RFI number | Sequential, never reused (047, 048…) |
| Date sent | When it left the GC |
| Subject | Location and problem in a few words |
| References | Sheet and revision, detail, grid, spec section |
| From | The sub or person who raised it |
| To | Architect or consultant it went to |
| Date required | When the answer is needed |
| Date answered | When the written answer came back |
| Status | Open, answered, closed, or void |
| Cost or time impact | Yes, no or possible, with the change order number if one follows |
| Linked documents | Marked-up page, photos, ASI or sketch received |
If your team marks up RFIs in Bluebeam Revu, its Markups List can be exported to a spreadsheet as a starting point; see how to export Bluebeam markups to Excel.
Frequently asked questions
What is the purpose of an RFI?
The purpose of an RFI is to get a written answer from the design team when the contract documents are unclear, incomplete or in conflict, so the contractor builds what the designer intended. It creates a record of the question and the answer. Under AIA A201–2017, it is also how the contractor reports errors, omissions and code issues it finds in the documents.
What is the difference between an RFI and an RFP?
An RFI in construction is a question about the contract documents asked during the job, usually by the contractor to the architect. An RFP (request for proposal) is sent before a contract is awarded, asking firms to propose a price and approach. In procurement, "RFI" can also mean an early request to vendors before an RFP.
What is an RFI and an RFA in construction?
An RFI is a request for information or interpretation about the drawings and specifications. An RFA is a request for approval, a term some firms and owners use to ask for sign-off on a substitution, a sample or a method. RFA isn't a standard AIA form, so its meaning and process vary; check what your project specifications call it.
Does an RFI response change the contract?
Not by itself. AIA's G716 summary says neither the request nor the response authorizes work that increases cost or time. Under A201–2017, if the contractor believes a response adds cost or time, it submits a claim, and a change to the work goes through a change order or a construction change directive. Other contracts set their own rules.
Who pays for delays caused by late RFI answers?
It depends on the contract. A201–2017 has the architect answer within agreed time limits or "with reasonable promptness," and sends cost and time claims to Article 15. Many projects set response times in Division 01. Log the date each RFI was sent and needed, and check your agreement and general conditions with your contracts lead.
Next steps
Pick the next open question on your job, write it against the checklist above, and cloud the conflict on the current sheet with the RFI number in the callout. To mark up the RFI page in Notch, open the PDF and start with Revision cloud (C) and Callout (Q); the construction PDF markup page shows the full tool set.